Vt. Officials Hope For More FEMA Culvert Help

Print More

Vermont officials are hoping a decision by the Federal Emergency Management Agency to cover the cost of replacing a culvert in Townshend destroyed by flooding from Tropical Storm Irene means more towns will be eligible for similar funding.

State officials announced late Friday that FEMA had agreed to pay about $100,000 more to replace the Townshend culvert after an appeal of a decision that previously ruled the project ineligible for full funding.

Vermont Recovery office Dave Rapaport says there are dozens of similar culvert projects across the state that could be worth about $6 million.

FEMA has already paid a portion of the $543,000 needed to replace a corrugated metal culvert with a concrete arch that allows the river to flow freely beneath it.